As a key aspect of a passenger’s trip, accesses and parking lots represent a crucial investment. Expanding the capacity of the short- and long-term parking lots will help improve the customer experience and quality of service. Aéroports de Lyon also focuses on road renovation and road service optimization projects within the site.

Concourse Terminals 1 and 3

  • Objectives
    → Open a passenger reception space in front of Terminal 1 and Terminal 3 with a drop-off area, a shuttle stop and a taxi drop-off.
    Project :
    → Create a concourse
  • Preliminary timeline : Completion 2016
  • Cost of operation : €4 million
  • Key figures
    • 10,000 m² concourse
    • Drop-off area, 100 spots

Expansion of long-term parking capacities

  • Objectives
    → Increase long-term parking capacity while preserving the quality of the parking areas
  • Project
    → Expand above-ground parking lots
  • Preliminary timeline : Completion of 2,000 spots every 3 years
  • Cost of operation : €25 million
  • Key figures : + 12 000 spots by 2010

Expansion of short-term parking capacities

  • Objectives
    → Increase capacity of spots near terminals by creating silo parking lots on P6, PR3 and P2
  • Project
    → Build above-ground covered parking lots with 3 to 6 levels depending on location
  • Preliminary timeline : Horizon 2020
  • Cost of operation : €25 million
  • Key figures : 3 000 spots

Road improvements at heart of site

  • Objectives
    → Handle forecasted traffic flow in 2025
    → Add an access loop to Terminal 3
    → Integrate green modes of travel
    → Improve parking lot servicing
  • Project
    → Adjust size of existing roads, add traffic circles in areas with traffic crossings and create an access road for Terminal 3
  • Preliminary timeline
    First phase: Completion 2013
    Second phase: Completion 2020
  • Cost of operation
    €7 million for first phase
    €6 million for second phase
  • Key figures
    • 3 km of roads
    • 2 traffic circles at 2 entrances to site

Redesign of South entrance to site

  • Objectives
    → Directly service real estate parks to south
  • Project
    → Create a new traffic circle at main South access and redesign roads
  • Preliminary timeline : Completion 2015
  • Cost of operation : €6 million
  • Key figures
    • 1 km of 2x2 lanes redesigned
    • 1 traffic circle for oversize vehicles