With a 150-hectare platform, CargoPort has the potential to develop its freight business and welcome a large number of operators. Its land reserve allows investors to locate new freight-related businesses. The zone’s improved road servicing and the Carex project are examples that emphasize Aéroports de Lyon’s policy of investing in the development of its intermodal freight activities.

Relocation of express freight cluster

  • Objectives
    → Relocate express freight cluster adjacent to new South aircraft parking area
  • Project
    → Build a building to house express freight operators
  • Preliminary timeline : Horizon 2017
  • Cost of operation : €7 million
  • Key figures
    • 6,000 m²
    • 4 aircraft stations with false contact

Private plot servicing

  • Objectives
    → Set up private investment projects tied to air freight and multimodal transportation
  • Project
    → Run networks to edge of plots and create access roads
  • Preliminary timeline : According to demand
  • Cost of operation : €3 million
  • Key figures : 50 ha on 6 to 8 plots

Direct south access cargoport

  • Objectives
    → Make the South access from A432 the main CargoPort entrance and separate the passenger and truck access roads
  • Project
    → Resize south access of Cargoport and create traffic circles that service the various zones
  • Preliminary timeline :
    First phase : Completion end 2011
    • Second phase: Completion end 2013
  • Cost of operation : €2.5 million
  • Key figures
    • 1.5 km of roads
    • 1 oversize entrance traffic circle and 3 servicing traffic circles